• 关于我们
    • 关于我们
    • 校园设施
    • 领导团队
    • 健康与安全
    • 协和国际教育发展基金
  • 招生入学
    • 招生部
    • 预约探校
    • 入学申请
    • 学费和费用标准
    • 入学要求
    • 常见问题
  • 课程设置
    • 课程设置
    • 学前部
    • 小学部
    • 初中部
    • 高中部
      • 全球在线学院
      • 大学先修课程
    • 应用学习
    • STEM
    • 中文课程
    • 学生支持
      • 升学指导
      • 英语辅助课程(ELL)
      • 学习辅助项目
  • 学生体验
    • 学生体验
    • 艺术素养
    • 体育与活动
    • 课外活动
    • 服务性学习
  • Concordia大家庭
    • Concordia大家庭
    • 校园新闻
    • 校友
    • 教职工
    • 家长参与
    • 学校服务
      • 技术支持
    • 校历
  • 工作机会
    • 工作机会
    • Employment Opportunities
    • Living in Shanghai
    • Frequently Asked Questions
关于我们
招生入学
课程设置
学生体验
Concordia大家庭
工作机会
EN
中
快速链接
  • 进入校园
  • 学校服务
  • 技术支持
  • 网络服务
家长后台

August-September Updates

Photo taken September 21, 2026

Construction on the new Rittmann Center continues to make steady progress. The below-ground structure was completed in mid-September, and work is now focused on the main building’s superstructure, which is expected to be completed in October.

Recent milestones include:

  • The completion of concrete pouring for the swimming pool area.

  • Continued construction in the theater area.

  • The installation of exterior scaffolding on the building’s second floor.

School leaders and members of the project team also visited the site to review a façade mock-up.

facade mockup

The Rittmann Center remains on schedule to open in fall 2027, bringing new spaces for athletics, the arts, wellness, and community life to the Concordia campus.

June-July Updates

RC update

The construction company completed excavation work in mid-June. Current work is focused on constructing the interior walls for the basement levels and pool area. The new building is scheduled to open in fall 2027.

February-March 2026 Updates

rittmann update feb mar
  • Retaining walls that protect the current buildings’ foundations were completed in January 2026.

  • The primary bracing to continue dirt removal was done in early February 2026.

  • Construction has started again last week.  The main construction activity in March and April will be dirt removal.  Security personnel are stationed at both the Huang Yang Road and Ming Yue Road gates whenever vehicles enter or exit the site.

  • Two tower cranes will be installed at the construction site by March 22.  For safety purpose, a protective cover is required to be installed on the sidewalk of Mingyue Road.  The cover will be constructed around March 21-22. The sidewalk will be temporarily blocked during the construction period. 

We sincerely appreciate the efforts of the construction teams and will continue to provide regular updates as the project progresses.

December 2025-January 2026 Updates

Rittmann construction site
  • All piling works were successfully completed in December 2025.

  • A construction access gate on Huang Yang Road was open in December 2025.  Security personnel are stationed at both the Huang Yang Road and Ming Yue Road gates whenever vehicles enter or exit the site.

  • The construction team is currently working on the retaining walls to protect the current buildings when the soil is being removed.  The retaining walls should be completed by January 2026. Construction activities will be suspended from February 12 to early March so the workers may return to their hometown for Chinese New Year. 

October-November 2025 Updates

true

Construction progress continues steadily as the team works hard to prepare the site for the major phases of work ahead.

  • This week, the construction company has been finalizing the setup of all on-site construction offices, which will serve as the coordination hub for the many teams involved in the project. 

  • To help maintain a clean and safe environment, the team has installed dust management sprayers along the perimeter walls to reduce airborne particles and protect both our students and the surrounding neighborhood.

  • In addition, a truck wash system has been installed at the site exit. Every truck is cleaned before leaving campus to ensure that dirt, dust, and mud are not tracked into the neighborhood — a key step in being a good neighbor during this long-term project.

  • Finally, test piling work is well underway and moving full speed ahead, with crews working diligently to stay on schedule and maintain safety across the site.

  • To support safe and orderly access, two security posts will be placed at the construction gate, with staff on duty during vehicle entry and exit. Additional contractor personnel will assist at peak drop-off and pick-up times.

We are grateful for the construction team’s effort and professionalism, and we will continue to provide regular updates as the project progresses.

July-September 2025 Updates

As you know, this summer marked an important step forward in Concordia’s reimagining of the Rittmann Center (RC).

  • During the summer months, the RC was carefully removed, with much of the material recycled in keeping with our commitment to sustainability. Click here to view a time-lapse of the RC coming down over a two-week period.  This is a powerful reminder of the progress already made.

  • Arts and Music classrooms were relocated into the PC building, where new spaces were created to support students and teachers.

  • A contractor with strong expertise in doing deep foundation work has been engaged to ensure safety for our students and existing buildings as the project moves forward.

  • The construction site is now being prepared for an expanded team of workers who will soon be onsite. At the same time, we are finalizing permits with local authorities so that full excavation for the new Performing Arts and Aquatics Center can begin.

The photos below show the current RC site, being covered to control dust during windy conditions.

 

true

We are excited about this next phase and remain committed to keeping our students safe and our community informed as Concordia’s campus continues to grow. 

Throughout the school year, we will continue to provide updates on the state of the RC project. 

Concordia International School Shanghai

345 Huangyang Road, Pudong, Shanghai, China, 201206

访客入口:上海浦东新区黄杨路345号

+8621 5899 0380
admissions@concordiashanghai.org
校历招生入学工作机会隐私政策员工目录学校博客
沪ICP备11020967号-1
infocare-logo